Hours: 64:00

Project Date User Activity Issue Comment Hours Status Author Created Target version Tracker Week Category Finish Date Start Date Engr, %effort Team_Size Milestone Reference Critical Path Severity
Kardib 18/06/2026 Gowri G Development Task #3689: SW development Verified that the UART, BLE and GUI 8:00 In Progress Gowri G 18/06/2026 01:35 PM Task 25 31/08/2026 01/05/2026 sumanth 30% Gowri 50% Mohan 10% 3 Actions
Kardib 16/06/2026 Gowri G Development Task #3689: SW development Run through the code and verified the bluetooth data and the UART terminal data 8:00 In Progress Gowri G 16/06/2026 12:51 PM Task 25 31/08/2026 01/05/2026 sumanth 30% Gowri 50% Mohan 10% 3 Actions
Kardib 16/06/2026 Gowri G Development Task #3689: SW development Run through the code and verified the bluetooth data and the UART terminal data 8:00 In Progress Gowri G 16/06/2026 12:50 PM Task 25 31/08/2026 01/05/2026 sumanth 30% Gowri 50% Mohan 10% 3 Actions
Kardib 11/06/2026 Gowri G Development Task #3689: SW development Tested and debugged the System console for printing the Data in DA14695 Board - Driver Installation 8:00 In Progress Gowri G 11/06/2026 02:21 PM Task 24 31/08/2026 01/05/2026 sumanth 30% Gowri 50% Mohan 10% 3 Actions
Kardib 09/06/2026 Gowri G Development Task #3689: SW development Started the SW developement with small SDK application 8:00 In Progress Gowri G 09/06/2026 02:02 PM Task 24 31/08/2026 01/05/2026 sumanth 30% Gowri 50% Mohan 10% 3 Actions
Kardib 09/06/2026 Gowri G Development Task #3689: SW development Started working on the Software Development 8:00 In Progress Gowri G 09/06/2026 01:59 PM Task 24 31/08/2026 01/05/2026 sumanth 30% Gowri 50% Mohan 10% 3 Actions
Kardib 09/06/2026 Gowri G Development Task #3691: tool chain test and flashing Tool chain test and flashing - Target DA14695 device using the J-Link SWD interface. 8:00 In Progress Gowri G 09/06/2026 01:54 PM Task 24 31/08/2026 01/05/2026 sumanth 30% Gowri 50% Mohan 10% 3 Actions
Kardib 08/06/2026 Gowri G Development Task #3691: tool chain test and flashing Tool chain test and flashing 8:00 In Progress Gowri G 09/06/2026 02:01 PM Task 24 31/08/2026 01/05/2026 sumanth 30% Gowri 50% Mohan 10% 3 Actions