03/07/2026 Thomas Joseph Development Task #3680: Project Planning and Review Review - Team Discussion 1:00 In Progress Thomas Joseph GW 2.2 03/07/2026 10:17 AM SAM E54 Platform - Zarro Integrated - mDAQ Lite Task 27 26/06/2026 01/06/2026 Mallikarjuna, Dhanasekar, Thomas Joseph, Venumadhav, Resmi 5 Actions
09/06/2026 Thomas Joseph Enquiry Task #3680: Project Planning and Review Sensor review and clarification with customer 1:30 In Progress Thomas Joseph GW 2.2 26/06/2026 05:41 PM SAM E54 Platform - Zarro Integrated - mDAQ Lite Task 24 26/06/2026 01/06/2026 Mallikarjuna, Dhanasekar, Thomas Joseph, Venumadhav, Resmi 5 Actions
08/06/2026 Thomas Joseph Development Task #3680: Project Planning and Review Delivery plan review, Clarification email 1:00 In Progress Thomas Joseph GW 2.2 26/06/2026 05:25 PM SAM E54 Platform - Zarro Integrated - mDAQ Lite Task 24 26/06/2026 01/06/2026 Mallikarjuna, Dhanasekar, Thomas Joseph, Venumadhav, Resmi 5 Actions
03/06/2026 Thomas Joseph Design Task #3680: Project Planning and Review Delivery plan 1:00 In Progress Thomas Joseph GW 2.2 26/06/2026 04:50 PM SAM E54 Platform - Zarro Integrated - mDAQ Lite Task 23 26/06/2026 01/06/2026 Mallikarjuna, Dhanasekar, Thomas Joseph, Venumadhav, Resmi 5 Actions