Hours: 16:00

Date User Activity Issue Comment Hours Status Author Project Created Target version Tracker Week Category Finish Date Start Date Engr, %effort Team_Size Severity
09/06/2026 Gowri G Development Task #3691: tool chain test and flashing Tool chain test and flashing - Target DA14695 device using the J-Link SWD interface. 8:00 In Progress Gowri G Kardib 09/06/2026 01:54 PM Task 24 31/08/2026 01/05/2026 sumanth 30% Gowri 50% Mohan 10% 3 Actions
08/06/2026 Gowri G Development Task #3691: tool chain test and flashing Tool chain test and flashing 8:00 In Progress Gowri G Kardib 09/06/2026 02:01 PM Task 24 31/08/2026 01/05/2026 sumanth 30% Gowri 50% Mohan 10% 3 Actions