Hours: 565:10

Date User Activity Issue Comment Hours Status Author Project Created Target version Tracker Week Category Finish Date Start Date Engr, %effort Team_Size Severity
09/01/2026 Thomas Joseph Meeting Task #2928: Testing of PLCIO Stacked boards with CTB platform Team review meeting 0:30 Resolved Thomas Joseph mDAQ4-1(Mid Range mDAQ)-Pilot 09/01/2026 07:04 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
09/01/2026 Dhanasekar T Procurement Task #2962: IO PCB Fabrication Quotation received and PR created 0:30 Resolved Dhanasekar T mTracker(Mid Range GW)-Pilot 09/01/2026 06:28 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
09/01/2026 Dhanasekar T Procurement Task #2936: Enclosure Procurement Procurement done 0:06 Resolved Dhanasekar T mTracker(Mid Range GW)-Pilot 09/01/2026 06:27 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
09/01/2026 Dhanasekar T Procurement Task #2940: Enclosure fabrication Enclosure moved to fabricator 0:30 Resolved Dhanasekar T mTracker(Mid Range GW)-Pilot 09/01/2026 06:25 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
09/01/2026 Dhanasekar T PCB assembly Task #2997: GW 2.0 PCB Assembly Components sent to uV for assembly 0:30 Resolved Dhanasekar T mDAQ4-1(Mid Range mDAQ)-Pilot 09/01/2026 06:22 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
09/01/2026 Thomas Joseph Documentation Task #2964: Product Requirements Product spec. document : Reviewed comments, formated and baselined 0:30 Resolved Thomas Joseph mTracker(Mid Range GW)-Pilot 09/01/2026 06:20 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
09/01/2026 Dhanasekar T Procurement Task #2996: GW 2.0 PCB Fabrication Process going on middle stage(40-80%) 0:06 Resolved Dhanasekar T mDAQ4-1(Mid Range mDAQ)-Pilot 09/01/2026 06:20 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
09/01/2026 Sumanth D Testing Task #2930: Test PLCIO with CTB application Testing 3:00 Resolved Sumanth D mDAQ4-1(Mid Range mDAQ)-Pilot 09/01/2026 05:55 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
09/01/2026 Channamallikarjuna Mattihalli Support Task #2968: SW-Development Request to Assign Task 2968 and Subtasks 1:00 In Progress Channamallikarjuna Mattihalli mTracker(Mid Range GW)-Pilot 09/01/2026 04:52 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Thomas Joseph Design Task #2984: Preliminary Design Arctitecture Study 1:00 In Progress Thomas Joseph mDAQ4-1(Mid Range mDAQ)-Pilot 08/01/2026 03:04 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Thomas Joseph Design Task #3017: Design of Enclosure Graphics(Sticker/Screenprint) review 0:15 Resolved Thomas Joseph mTracker(Mid Range GW)-Pilot 08/01/2026 02:34 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Thomas Joseph Meeting Task #2935: Procurement Procurement Review 0:30 In Progress Thomas Joseph mTracker(Mid Range GW)-Pilot 08/01/2026 02:09 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Thomas Joseph Design Task #2934: Detailed Design PCB Design Review 2:00 In Progress Thomas Joseph mTracker(Mid Range GW)-Pilot 08/01/2026 02:00 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Sumanth D Testing Task #2928: Testing of PLCIO Stacked boards with CTB platform Testing PLCIO PCB's 8:00 Resolved Sumanth D mDAQ4-1(Mid Range mDAQ)-Pilot 08/01/2026 01:38 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Thomas Joseph redmine review/ update Task #3039: Project Planning and Review Planning and Review 0:30 In Progress Thomas Joseph mDAQ4-1(Mid Range mDAQ)-Pilot 08/01/2026 01:33 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Thomas Joseph Meeting Task #3039: Project Planning and Review Review and steering meeting with DM 0:30 In Progress Thomas Joseph mDAQ4-1(Mid Range mDAQ)-Pilot 08/01/2026 01:32 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Thomas Joseph Meeting Task #3039: Project Planning and Review Team review meeting 0:30 In Progress Thomas Joseph mDAQ4-1(Mid Range mDAQ)-Pilot 08/01/2026 01:31 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Thomas Joseph Meeting Task #3038: Project Planning and Review Team review meeting 0:30 In Progress Thomas Joseph mTracker(Mid Range GW)-Pilot 08/01/2026 01:28 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Thomas Joseph Meeting Task #3038: Project Planning and Review Review and steering meeting with DM 0:30 In Progress Thomas Joseph mTracker(Mid Range GW)-Pilot 08/01/2026 01:27 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Thomas Joseph redmine review/ update Task #3038: Project Planning and Review Planning and Review 0:30 In Progress Thomas Joseph mTracker(Mid Range GW)-Pilot 08/01/2026 01:25 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Prakash M Testing Task #2930: Test PLCIO with CTB application AI value has been gotten with PLC_IO controller. DI,DO verification with PLC_IO controller is in process. 6:00 Resolved Prakash M mDAQ4-1(Mid Range mDAQ)-Pilot 08/01/2026 01:21 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Dhanasekar T Procurement Task #2996: GW 2.0 PCB Fabrication Prcoess going on 0:30 Resolved Dhanasekar T mDAQ4-1(Mid Range mDAQ)-Pilot 08/01/2026 07:55 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Dhanasekar T Procurement Task #2936: Enclosure Procurement Screen printing enquiry to creative printers 1:00 Resolved Dhanasekar T mTracker(Mid Range GW)-Pilot 08/01/2026 07:33 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Dhanasekar T Procurement Task #2936: Enclosure Procurement Design file sent to SRS enterprises 1:00 Resolved Dhanasekar T mTracker(Mid Range GW)-Pilot 08/01/2026 07:31 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
08/01/2026 Dhanasekar T Procurement Task #2936: Enclosure Procurement Payment done and design sent to supplier and verified 0:30 Resolved Dhanasekar T mTracker(Mid Range GW)-Pilot 08/01/2026 07:29 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
07/01/2026 Surendra Naik PCB assembly Task #2929: PLCIO Interface PCB Assembly mounting for the PLC I/O interface PCB 8:00 Resolved Surendra Naik mDAQ4-1(Mid Range mDAQ)-Pilot 07/01/2026 01:17 PM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
07/01/2026 Sumanth D Testing Task #2928: Testing of PLCIO Stacked boards with CTB platform PLCIO testing 3:00 Resolved Sumanth D mDAQ4-1(Mid Range mDAQ)-Pilot 07/01/2026 06:02 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
07/01/2026 Dhanasekar T Procurement Task #2996: GW 2.0 PCB Fabrication PR created and order placed 0:30 Resolved Dhanasekar T mDAQ4-1(Mid Range mDAQ)-Pilot 07/01/2026 04:59 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
07/01/2026 Dhanasekar T PCB assembly Task #2997: GW 2.0 PCB Assembly Sent BoM to uV for quotation 0:30 Resolved Dhanasekar T mDAQ4-1(Mid Range mDAQ)-Pilot 07/01/2026 04:58 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
07/01/2026 Dhanasekar T Mechanical Assembly Task #2970: Parts List(Mech. Assembly) Parts list created 0:06 Resolved Dhanasekar T mTracker(Mid Range GW)-Pilot 07/01/2026 04:53 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
07/01/2026 Dhanasekar T Procurement Task #2936: Enclosure Procurement Approval request 0:06 Resolved Dhanasekar T mTracker(Mid Range GW)-Pilot 07/01/2026 04:50 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
07/01/2026 Dhanasekar T Procurement Task #2936: Enclosure Procurement Quotation received and PR created 1:00 Resolved Dhanasekar T mTracker(Mid Range GW)-Pilot 07/01/2026 04:49 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
07/01/2026 Dhanasekar T Procurement Task #2927: N58 Module Procurement Board received 0:06 Resolved Dhanasekar T mTracker(Mid Range GW)-Production 07/01/2026 04:47 AM Task 2 31/03/2026 02/01/2026 Thomas(30%), Venumadhav(100%),Dhilip(20%) 3 Actions
06/01/2026 Sumanth D Testing Task #2928: Testing of PLCIO Stacked boards with CTB platform PLCIO testing 1:00 Resolved Sumanth D mDAQ4-1(Mid Range mDAQ)-Pilot 06/01/2026 09:51 AM Task 2 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions