Hours: 233:21

Date User Activity Issue Comment Hours Status Author Project Created Target version Tracker Week Category Finish Date Start Date Engr, %effort Team_Size Severity
04/03/2026 Jagatheswaran J Testing Task #2917: System Test Results and Reports device testing 8:00 Analysis Started Jagatheswaran J Chola Turbo Machinery Pvt Ltd 06/03/2026 07:18 AM Task 10 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
24/02/2026 Jagatheswaran J Testing Task #2917: System Test Results and Reports device testing 4:00 Analysis Started Jagatheswaran J Chola Turbo Machinery Pvt Ltd 24/02/2026 12:38 PM Task 9 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
10/02/2026 Thomas Joseph Support Task #3239: Installation Support TIA Software Uninstallation 0:30 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 11/02/2026 04:15 AM Task 7 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
10/02/2026 Thomas Joseph Development Task #2915: EREMOS Development Data update 0:30 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 10/02/2026 05:39 AM Task 7 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/02/2026 Jagatheswaran J Testing Task #2917: System Test Results and Reports testcase document update 8:00 Analysis Started Jagatheswaran J Chola Turbo Machinery Pvt Ltd 10/02/2026 10:11 AM Task 7 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/02/2026 Thomas Joseph Support Task #3239: Installation Support TIA Installation 3:00 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 09/02/2026 05:11 PM Task 7 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/02/2026 Thomas Joseph Development Task #3243: ConfigPacket (Split, Delay) Discussion on plan & review 0:30 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 09/02/2026 08:32 AM Task 7 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/02/2026 Thomas Joseph Support Task #3239: Installation Support Installation Report Generation 1:00 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 09/02/2026 08:32 AM Task 7 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
07/02/2026 Thomas Joseph Support Task #3239: Installation Support Installation at Customer Site 8:00 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 08/02/2026 08:11 AM Task 6 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
06/02/2026 Thomas Joseph Support Task #3239: Installation Support Installation at Customer Site 10:00 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 08/02/2026 08:11 AM Task 6 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
05/02/2026 Jagatheswaran J Testing Task #2917: System Test Results and Reports testing 6:00 Analysis Started Jagatheswaran J Chola Turbo Machinery Pvt Ltd 05/02/2026 12:48 PM Task 6 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
05/02/2026 Jagatheswaran J Testing Task #2917: System Test Results and Reports testing 4:00 Analysis Started Jagatheswaran J Chola Turbo Machinery Pvt Ltd 05/02/2026 05:44 AM Task 6 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
02/02/2026 Thomas Joseph Support Task #3239: Installation Support Installation at Customer Site 10:00 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 05/02/2026 08:10 AM Task 6 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
02/02/2026 Jagatheswaran J Testing Task #2917: System Test Results and Reports testing 8:00 Analysis Started Jagatheswaran J Chola Turbo Machinery Pvt Ltd 03/02/2026 06:21 AM Task 6 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
01/02/2026 Jagatheswaran J Testing Task #2917: System Test Results and Reports device testing 8:00 Analysis Started Jagatheswaran J Chola Turbo Machinery Pvt Ltd 02/02/2026 07:45 AM Task 5 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
30/01/2026 Thomas Joseph Support Task #3239: Installation Support Installation at Customer Site 12:00 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 05/02/2026 08:11 AM Task 5 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
29/01/2026 Thomas Joseph Documentation Task #2958: Product Requirements Product Spec. document update 0:30 Resolved Thomas Joseph Chola Turbo Machinery Pvt Ltd 29/01/2026 05:24 AM Task 5 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
28/01/2026 Dhanasekar T Procurement Task #2942: Procurement Done 0:06 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 28/01/2026 06:34 AM Task 5 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
28/01/2026 Dhanasekar T Dispatch Task #2916: Proto 1 Delivery to Chola Device Delivered to customer 0:06 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 28/01/2026 06:29 AM Task 5 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
27/01/2026 Thomas Joseph Development Task #3037: Project Planning and Review review 0:15 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 27/01/2026 07:09 AM Task 5 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
22/01/2026 Dhanasekar T Documentation Task #2955: Parts List(Mech. Assembly) Done 0:30 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 22/01/2026 01:07 PM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
22/01/2026 Prakash M Development Task #3021: E-REMOS device configuration & Dashboard setup Data posting -side development is in process(linux platform) 8:00 In Progress Prakash M Chola Turbo Machinery Pvt Ltd 22/01/2026 01:04 PM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
21/01/2026 Prakash M Development Task #3021: E-REMOS device configuration & Dashboard setup Config packet verification is in process on device side. 7:00 In Progress Prakash M Chola Turbo Machinery Pvt Ltd 21/01/2026 01:15 PM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
21/01/2026 Jagatheswaran J Testing Task #2913: Test Plan Development and Approvals Test case Document update 8:00 In Progress Jagatheswaran J Chola Turbo Machinery Pvt Ltd 21/01/2026 10:19 AM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
20/01/2026 Thomas Joseph redmine review/ update Task #3037: Project Planning and Review Planning and Review 0:30 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 20/01/2026 04:00 PM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
20/01/2026 Jagatheswaran J Documentation Task #2913: Test Plan Development and Approvals testcase document update 4:00 In Progress Jagatheswaran J Chola Turbo Machinery Pvt Ltd 20/01/2026 01:04 PM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
20/01/2026 Dhanasekar T Procurement Task #2938: Enclosure fabrication Document updated 0:30 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 20/01/2026 09:05 AM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
20/01/2026 Prakash M Development Task #3021: E-REMOS device configuration & Dashboard setup The Modbus parameter names were corrected after updating the placeholders(limits) on the UI. 3:00 In Progress Prakash M Chola Turbo Machinery Pvt Ltd 20/01/2026 08:24 AM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
19/01/2026 Jagatheswaran J Testing Task #2913: Test Plan Development and Approvals testcase document update 4:00 In Progress Jagatheswaran J Chola Turbo Machinery Pvt Ltd 19/01/2026 01:06 PM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
19/01/2026 Thomas Joseph Meeting Task #3037: Project Planning and Review Critical Project Update call 1:00 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 19/01/2026 11:21 AM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
19/01/2026 Dhanasekar T Procurement Task #2938: Enclosure fabrication Machining and laser marking completed 0:06 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 19/01/2026 05:32 AM Task 4 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
16/01/2026 Thomas Joseph Mechanical Assembly Task #2947: Mechanical Assembly Review of assembly issues and resolution 1:00 Resolved Thomas Joseph Chola Turbo Machinery Pvt Ltd 16/01/2026 03:01 PM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
16/01/2026 Thomas Joseph Meeting Task #3037: Project Planning and Review Critical Project Update call 0:45 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 16/01/2026 02:58 PM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
16/01/2026 Thomas Joseph Testing Task #2948: USB PCB Testing Assembly and test review and support 1:00 Resolved Thomas Joseph Chola Turbo Machinery Pvt Ltd 16/01/2026 02:55 PM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
16/01/2026 Prakash M Development Task #3021: E-REMOS device configuration & Dashboard setup Config packet list verification is in process. 1:00 In Progress Prakash M Chola Turbo Machinery Pvt Ltd 16/01/2026 02:14 PM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
16/01/2026 Prakash M Development Task #3021: E-REMOS device configuration & Dashboard setup All Modbus parameters (real data type and alarm-based bit fields) have been added to the dashboard 4:00 In Progress Prakash M Chola Turbo Machinery Pvt Ltd 16/01/2026 06:34 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
14/01/2026 Thomas Joseph Meeting Task #3037: Project Planning and Review Critical Project Update call 2:00 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 14/01/2026 11:08 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
14/01/2026 Thomas Joseph Review document Task #2913: Test Plan Development and Approvals Test case doc. review 0:30 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 14/01/2026 08:00 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
14/01/2026 Jagatheswaran J Documentation Task #2913: Test Plan Development and Approvals Test case Document 8:00 In Progress Jagatheswaran J Chola Turbo Machinery Pvt Ltd 14/01/2026 07:19 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
14/01/2026 Thomas Joseph Testing Task #2947: Mechanical Assembly Review of Assembly Issues 0:45 Resolved Thomas Joseph Chola Turbo Machinery Pvt Ltd 14/01/2026 07:05 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
14/01/2026 Thomas Joseph Meeting Task #3037: Project Planning and Review Status meeting discussion on action items 0:30 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 14/01/2026 07:04 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
14/01/2026 Dhanasekar T Mechanical Assembly Task #2947: Mechanical Assembly Mechanical assembly report 1:00 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 14/01/2026 06:36 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
14/01/2026 Thomas Joseph Documentation Task #2956: Preliminary Design Prelim. Design Documentation 0:45 Resolved Thomas Joseph Chola Turbo Machinery Pvt Ltd 14/01/2026 05:30 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
13/01/2026 Surendra Naik PCB assembly Task #2946: USB PCB Assembly Usb pcb assembly 6:00 Resolved Surendra Naik Chola Turbo Machinery Pvt Ltd 13/01/2026 05:03 PM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
13/01/2026 Thomas Joseph redmine review/ update Task #3037: Project Planning and Review Plan revision 0:45 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 13/01/2026 02:25 PM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
13/01/2026 Dhanasekar T Procurement Task #3071: Enclosure Screen Printing Screen printing file sent to fabricator 0:30 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 13/01/2026 01:26 PM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
13/01/2026 Prakash M Development Task #3021: E-REMOS device configuration & Dashboard setup A real (floating-point) data type Modbus parameter has been added to E-REMOS. 5:00 In Progress Prakash M Chola Turbo Machinery Pvt Ltd 13/01/2026 12:47 PM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
13/01/2026 Thomas Joseph Meeting Task #3037: Project Planning and Review Team review meeting - Resource/Timeline 0:45 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 13/01/2026 05:53 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
12/01/2026 Thomas Joseph Meeting Task #3037: Project Planning and Review Planning and Review 0:20 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 13/01/2026 03:33 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
12/01/2026 Thomas Joseph Meeting Task #3037: Project Planning and Review Critical Project Update call 1:00 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 13/01/2026 03:32 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
12/01/2026 Channamallikarjuna Mattihalli Development Task #2953: Modbus-TCP Modbus TCP reading data from Server i.e PLC we used software MODBUS SIM 8:00 In Progress Channamallikarjuna Mattihalli Chola Turbo Machinery Pvt Ltd 12/01/2026 01:04 PM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
12/01/2026 Jagatheswaran J Documentation Task #2913: Test Plan Development and Approvals testcase document update 6:00 In Progress Jagatheswaran J Chola Turbo Machinery Pvt Ltd 12/01/2026 11:37 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
12/01/2026 Channamallikarjuna Mattihalli Development Task #2953: Modbus-TCP Modbus TCP on SAME54 controller to read PLC data 8:00 In Progress Channamallikarjuna Mattihalli Chola Turbo Machinery Pvt Ltd 12/01/2026 03:55 AM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
12/01/2026 Thomas Joseph Documentation Task #2957: Customer Requirements Finalisation customer requirement documentation 1:30 Resolved Thomas Joseph Chola Turbo Machinery Pvt Ltd 11/01/2026 02:46 PM Task 3 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/01/2026 Thomas Joseph Design Task #2960: Wiring Diagram Wiring diagram planning 1:00 Resolved Thomas Joseph Chola Turbo Machinery Pvt Ltd 10/01/2026 05:03 PM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/01/2026 Jagatheswaran J Documentation Task #2913: Test Plan Development and Approvals testcase document update 4:00 In Progress Jagatheswaran J Chola Turbo Machinery Pvt Ltd 09/01/2026 11:32 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/01/2026 Thomas Joseph redmine review/ update Task #3037: Project Planning and Review Task/Resource allocation, Time log 0:45 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 09/01/2026 11:01 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/01/2026 Thomas Joseph Meeting Task #3037: Project Planning and Review Critical Project Update call 1:10 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 09/01/2026 10:52 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/01/2026 Dhanasekar T Procurement Task #2939: Enclosure Procurement Done 0:06 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 09/01/2026 07:54 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/01/2026 Dhanasekar T Procurement Task #2961: USB PCB Fabrication Quotation received and PR created 2:00 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 09/01/2026 06:18 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/01/2026 Dhanasekar T Procurement Task #2938: Enclosure fabrication Enclosure moved to fabricator 1:00 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 09/01/2026 06:17 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
09/01/2026 Dhanasekar T Procurement Task #2939: Enclosure Procurement Procurement done 1:00 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 09/01/2026 06:14 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
08/01/2026 Thomas Joseph Design Task #3040: Design of Enclosure Graphics(Sticker/Screenprint) review 0:15 Resolved Thomas Joseph Chola Turbo Machinery Pvt Ltd 08/01/2026 02:35 PM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
08/01/2026 Thomas Joseph Documentation Task #2911: PLC MODBUS mapping from Chola on Siemens PLC customer requirement documentation 0:15 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 08/01/2026 01:58 PM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
08/01/2026 Thomas Joseph redmine review/ update Task #3037: Project Planning and Review Planning and Review 0:30 In Progress Thomas Joseph Chola Turbo Machinery Pvt Ltd 08/01/2026 01:20 PM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
08/01/2026 Dhanasekar T Documentation Task #2958: Product Requirements Screen printing attached 0:06 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 08/01/2026 12:35 PM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
08/01/2026 Jagatheswaran J Testing Task #2913: Test Plan Development and Approvals Test case document preparation based on the CSR document. 8:00 In Progress Jagatheswaran J Chola Turbo Machinery Pvt Ltd 08/01/2026 11:24 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
08/01/2026 Channamallikarjuna Mattihalli Development Task #2954: TCP Over 4G 4G 8:00 Resolved Channamallikarjuna Mattihalli Chola Turbo Machinery Pvt Ltd 08/01/2026 09:41 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
08/01/2026 Channamallikarjuna Mattihalli Development Task #2954: TCP Over 4G 4G TCP 8:00 Resolved Channamallikarjuna Mattihalli Chola Turbo Machinery Pvt Ltd 08/01/2026 09:40 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
08/01/2026 Channamallikarjuna Mattihalli Development Task #2954: TCP Over 4G 4G TCP 8:00 Resolved Channamallikarjuna Mattihalli Chola Turbo Machinery Pvt Ltd 08/01/2026 09:39 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
07/01/2026 Dhanasekar T Mechanical Assembly Task #2938: Enclosure fabrication Sent mail to supplier 1:00 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 07/01/2026 05:19 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
07/01/2026 Dhanasekar T Procurement Task #2939: Enclosure Procurement Quotation received and PR created 0:06 Resolved Dhanasekar T Chola Turbo Machinery Pvt Ltd 07/01/2026 05:14 AM Task 2 31/03/2026 24/12/2025 VenuM 50%, Neha 100%, Dhan40%, Greeshma 50%, Mallikar100% 4 Actions
    (1-72/72)