Actions
Task #3520
openMechanical Fabrication
Task #3520:
Mechanical Fabrication
Start date:
20/04/2026
Due date:
09/06/2026 (about 3 months late)
% Done:
100%
Estimated time:
Spent time:
Updated by Thomas Joseph 5 months ago
- Due date changed from 27/03/2026 to 27/04/2026
- Start date changed from 20/03/2026 to 20/04/2026
Updated by Thomas Joseph 3 months ago
ยท Edited
Inform Venu sir about V300 design
Initiate with Deeksha
Updated by Thomas Joseph 3 months ago
- Due date changed from 27/04/2026 to 09/06/2026
Due date changed from 20/04/2026 to 03/06/2026
Due date extended based on http://5.161.106.25:3000/issues/3662#note-1
- use v300 carry case
- Top panel fabrication and screen printing
- V300 frame fabrication including bottom plate
- bottom plate clamp fabrication
- cable assembly
Updated by Thomas Joseph 3 months ago
- Status changed from New to In Progress
- % Done changed from 0 to 20
Meeting discussion (VM, DT, BSN)
-Check waveshare display, depth, availability, order if we get in this week
-followup Top plate design with Shiva
-update bottom plate design
---use actual size of all components, boxes
---add cable entry for all, with bending radius, mini pc fins
---fix mini pc direction
---consider an exhaust fan
---ISP box add in design
-Decide clamp after completing the bottom plate design
Updated by Thomas Joseph 3 months ago
9/06/2026
Clamp fab completed
Updated by Thomas Joseph 3 months ago
- % Done changed from 20 to 100
18/06/2026
Top plate fabrication completed and received
All fabrication completed