Task #3222

open

Project Planning and Review

Task #3222: Project Planning and Review

Added by Thomas Joseph 8 months ago. Updated 2 months ago.

Status:
In Progress
Priority:
Normal
Assignee:
Target version:
-
Start date:
05/01/2026
Due date:
31/07/2026 (38 days late)
% Done:

50%

Estimated time:
Spent time:

Description

For time-sheet reporting purpose ONLY based on email from HR dated 08/01/2026 Subject: Mandatory Submission of Weekly Timesheet

Updated by Thomas Joseph 7 months ago Actions #1

  • Due date changed from 16/02/2026 to 07/03/2026

Updated by Thomas Joseph 7 months ago Actions #2

  • % Done changed from 0 to 30

Updated by Thomas Joseph 7 months ago Actions #3

Teams meeting : Discussion on following Projects/Products
(SV, VK, TJ)
N58 Open CPU

  • HW - PCB Design , Mechanical
  • SW -
  • Dhilip for PCB design
  • Buy open CPU module and start s/w development

E54 Platform

  • Core4 RTU is the super set - Controller PCB, IO PCB, PLCIO PCB

Jubilant
-SW

VAS
List functions and assign resources
Mohan and Devipriyaa (rpm, sync-in, sync-out, delay in throughput, FFT in device)
Yoganand

TPMS - Very high priority
Mohan

CABS

Linux - EIDOS

Updated by Thomas Joseph 2 months ago Actions #4

  • Due date changed from 07/03/2026 to 31/07/2026
  • % Done changed from 30 to 50

Teams meeting(@Venu Krishnamurthy & team members)

Virajpet Delivery - 4 mTrackerLite and 2 mDAQ RTU (total 6 Nos)
27/6 2pm update

  1. Enclsosures (Dhilip has already collected with Screen print and cut outs) - Done

  2. Connector PCBs received today - Done

  3. PLCIO pcb testing - Resmi,
    first board AI completed, DI/DO testing pending.
    1st board testing completed, will be handed over to Malli
    2nd board testing to be done and handed over to Malli.

  4. Diagnostic tests SW - malli (to help Resmi test the PLCIO boards) -
    Stress/Load testing on 4G, LAN and SDcard testing
    SW binary - Malli
    HW setup - Resmi/Sumanth
    Testing - Chethan
    No issues detected for the above tests.
    No current measurements done, Resmi will handover DMM after testing PLCIO board

  5. mTracker lite enclosure assembly - surendra.
    4 enclosures completed, ready for system testing. Chethan/Malli to get started
    1 SAME54 controller to be replaced, berg connectors to be mounted.

  6. mTrackerLite System testing - Chethan, Pls keep submitting the test reports
    Chethan to share the current test reports

  7. Connector PCB Components -
    received all connectors except right angle connector. expected today.

  8. Connector PCBs assembly - Surendra
    2 boards to be assembled. have 1 backup, waiting for the right angle connector.

  9. mDAQ RTU Enclsoure assembly mDAQ RTU - Surendra/Dhilip
    Surendra to assemble and keep passing on to Malli/Chethan to start testing the device.

  10. mDAQ RTU System testing - Chethan
    full system test to be planned on Sunday.
    SW/HW fixes - Malli and Resmi

  11. GPS Led not functional. GPS not enabled in SW. Malli to confirm. Plan for next release