Task #3045

open
TJ TJ

Detailed Design

Task #3045: Detailed Design

Added by Thomas Joseph 2 months ago. Updated 16 days ago.

Status:
Analysis Started
Priority:
Normal
Assignee:
Target version:
-
Start date:
05/01/2026
Due date:
05/03/2026 (6 days late)
% Done:

17%

Estimated time:
(Total: 0:00 h)
Spent time:
(Total: 117:30 h)

Description

PCB Design, Mechanical Design, SW Design, Assembly Manual, Test Plan and Procedure


Subtasks 12 (12 open0 closed)

Task #3189: Design and Development of PLCIO PCBIn ProgressThomas Joseph05/01/202617/02/2026

Actions
Task #3191: PCB DesignIn ProgressResmi K.V02/02/202617/02/2026

Actions
Task #3192: Schematic DesignIn ProgressThomas Joseph05/01/202611/02/2026

Actions
Task #3253: BoMNewThomas Joseph11/02/202612/02/2026

Actions
Task #3195: Design of Enclosure CutoutsNewVenuMadhav S18/02/202620/02/2026

Actions
Task #3202: Wiring DiagramNewVenuMadhav S17/02/202618/02/2026

Actions
Task #3203: E-REMOS DevelopmentNew12/02/202605/03/2026

Actions
Task #3204: Embedded SW-DevelopmentNewDEVI PRIYAA25/02/202625/02/2026

Actions
Task #3221: GW2.0 Codebase readiness(Release 3.0)NewDEVI PRIYAA25/02/202625/02/2026

Actions
Task #3218: Design of Enclosure Graphics(Sticker/Screenprint)NewVenuMadhav S18/02/202620/02/2026

Actions
Task #3223: Test Plan Development and ApprovalsIn ProgressJagatheswaran J09/02/202616/02/2026

Actions
Task #3224: Review/Update of GW2.0 Test Plan and ProcedureNewVenuMadhav S18/02/202620/02/2026

Actions
Actions