Task #2996
openTask #2992: Procurement
GW 2.0 PCB Fabrication
Task #2996:
GW 2.0 PCB Fabrication
Added by Thomas Joseph 4 months ago. Updated about 2 months ago.
Files
| EITSPL-QR-PUR-06 Purchase Requisition (DT58_Circuit system).xlsx (31.8 KB) EITSPL-QR-PUR-06 Purchase Requisition (DT58_Circuit system).xlsx | Dhanasekar T, 07/01/2026 04:59 AM |
Updated by Dhanasekar T 4 months ago
Actions
#1
- File EITSPL-QR-PUR-06 Purchase Requisition (DT58_Circuit system).xlsx EITSPL-QR-PUR-06 Purchase Requisition (DT58_Circuit system).xlsx added
- Status changed from New to In Progress
- % Done changed from 0 to 40
PR created and order placed.
Updated by Dhanasekar T 4 months ago
Actions
#2
The PCB power is showing status-initial stage (0-40%).
Updated by Dhanasekar T 4 months ago
Actions
#3
- % Done changed from 40 to 60
Process going on middle stage(40-80%)
Updated by Dhanasekar T 4 months ago
Actions
#4
- Status changed from In Progress to Resolved
- % Done changed from 60 to 100
PCB received
Updated by Sunder Venugopal about 2 months ago
Actions
#5
- Due date changed from 09/03/2026 to 24/03/2026
- Start date changed from 02/03/2026 to 17/03/2026
- Follows Task #2993: Enclosure fabrication added
Updated by Sunder Venugopal about 2 months ago
Actions
#6
- Follows deleted (Task #2993: Enclosure fabrication)
Updated by Sunder Venugopal about 2 months ago
Actions
#7
- Related to Task #2993: Enclosure fabrication added
Updated by Sunder Venugopal about 2 months ago
Actions
#8
- Related to deleted (Task #2993: Enclosure fabrication)
Updated by Sunder Venugopal about 2 months ago
Actions
#9
- Has duplicate Task #2993: Enclosure fabrication added
Updated by Sunder Venugopal about 2 months ago
Actions
#10
- Start date changed from 17/03/2026 to 02/03/2026
Updated by Sunder Venugopal about 2 months ago
Actions
#11
- Due date changed from 24/03/2026 to 13/03/2026
Updated by Sunder Venugopal about 2 months ago
Actions
#12
- Has duplicate deleted (Task #2993: Enclosure fabrication)
Updated by Sunder Venugopal about 2 months ago
Actions
#13
- Related to Task #2993: Enclosure fabrication added
Updated by Sunder Venugopal about 2 months ago
Actions
#14
- Related to deleted (Task #2993: Enclosure fabrication)
Updated by Sunder Venugopal about 2 months ago
Actions
#15
- Is duplicate of Task #2993: Enclosure fabrication added
Updated by Sunder Venugopal about 2 months ago
Actions
#16
- Is duplicate of deleted (Task #2993: Enclosure fabrication)
Updated by Sunder Venugopal about 2 months ago
Actions
#17
- Blocked by Task #2993: Enclosure fabrication added
Updated by Sunder Venugopal about 2 months ago
Actions
#18
- Blocked by Task #2997: GW 2.0 PCB Assembly added
Updated by Sunder Venugopal about 2 months ago
Actions
#19
- Blocked by deleted (Task #2993: Enclosure fabrication)
Updated by Sunder Venugopal about 2 months ago
Actions
#20
- Blocked by deleted (Task #2997: GW 2.0 PCB Assembly)
Updated by Sunder Venugopal about 2 months ago
Actions
#21
- Blocked by Task #2993: Enclosure fabrication added
Updated by Sunder Venugopal about 2 months ago
Actions
#22
- Blocks Task #2997: GW 2.0 PCB Assembly added
Actions