Task #2988
closedTask #2985: Detailed Design
Design and Development of GW IF PCB
Task #2988:
Design and Development of GW IF PCB
Start date:
20/03/2026
Due date:
02/04/2026
% Done:
20%
Estimated time:
Description
this is to interface b/w GW2.0 controller PCB, 4G PCB and PLCIO PCBs
Updated by VenuMadhav S 4 months ago
- % Done changed from 0 to 20
As per plan PLC IO and Gateway boards integration completed
Updated by Thomas Joseph 4 months ago
- Due date changed from 10/01/2026 to 20/01/2026
- Status changed from New to Analysis Started
Updated by Thomas Joseph 4 months ago
- Status changed from Analysis Started to Closed
As per the new plan, the interface PCB is not required.
Refer => http://5.161.106.25:3000/issues/2986#note-5
Task is no longer required. Hence closed