Project

General

Profile

Actions

Task #2957

open
TJ SV

Customer Requirements Finalisation

Task #2957: Customer Requirements Finalisation

Added by Thomas Joseph 2 months ago. Updated about 2 months ago.

Status:
Resolved
Priority:
Normal
Target version:
-
Start date:
16/12/2025
Due date:
17/12/2025 (about 3 months late)
% Done:

100%

Estimated time:
Spent time:

Related issues 5 (5 open0 closed)

Blocked by Chola Turbo Machinery Pvt Ltd - Task #2958: Product RequirementsResolvedVenu Krishnamurthy17/12/202519/12/2025

Actions
Precedes Chola Turbo Machinery Pvt Ltd - Task #2956: Preliminary DesignResolvedVenuMadhav S18/12/202519/12/2025

Actions
Precedes Chola Turbo Machinery Pvt Ltd - Task #2915: EREMOS DevelopmentIn ProgressNeha K02/01/202626/01/2026

Actions
Precedes Chola Turbo Machinery Pvt Ltd - Task #2941: Detailed DesignIn ProgressVenuMadhav S18/12/202506/02/2026

Actions
Precedes Chola Turbo Machinery Pvt Ltd - Task #2952: Embedded SW-DevelopmentIn ProgressChannamallikarjuna Mattihalli18/12/202506/02/2026

Actions
Actions

Also available in: PDF Atom