Actions
Task #2916
open
SV
DT
Proto 1 Delivery to Chola
Task #2916:
Proto 1 Delivery to Chola
Description
Integration, Test and Packing
Gateway 2.0 box with eREMOS Software
SV Updated by Sunder Venugopal 2 months ago
- Due date changed from 19/01/2026 to 05/02/2026
- Start date changed from 02/01/2026 to 21/01/2026
- Follows Task #2917: System Test Results and Reports added
SV Updated by Sunder Venugopal 2 months ago
- Due date changed from 05/02/2026 to 03/02/2026
- Start date changed from 21/01/2026 to 19/01/2026
SV Updated by Sunder Venugopal 2 months ago
- Due date changed from 03/02/2026 to 19/02/2026
SV Updated by Sunder Venugopal 2 months ago
- Due date changed from 19/02/2026 to 19/01/2026
SV Updated by Sunder Venugopal 2 months ago
- Due date changed from 19/01/2026 to 20/01/2026
- Start date changed from 19/01/2026 to 20/01/2026
VS Updated by VenuMadhav S 2 months ago
Analysis completed.
Based upon analysis connector PCB needs to redesign. The design was started
TJ Updated by Thomas Joseph 2 months ago
- Assignee changed from VenuMadhav S to Dhanasekar T
SV Updated by Sunder Venugopal 2 months ago
- Follows Task #2945: Testing added
TJ Updated by Thomas Joseph about 2 months ago
- Due date changed from 20/01/2026 to 22/01/2026
- Start date changed from 20/01/2026 to 22/01/2026
SV Updated by Sunder Venugopal about 2 months ago
- Due date changed from 22/01/2026 to 27/01/2026
- Start date changed from 22/01/2026 to 27/01/2026
SV Updated by Sunder Venugopal about 2 months ago
- Due date changed from 21/01/2026 to 26/01/2026
- Start date changed from 21/01/2026 to 26/01/2026
TJ Updated by Thomas Joseph about 2 months ago
- Due date changed from 02/02/2026 to 11/02/2026
- Start date changed from 02/02/2026 to 11/02/2026
TJ Updated by Thomas Joseph about 1 month ago
- Due date changed from 23/01/2026 to 27/01/2026
Due date extended after demo on 24th
TJ Updated by Thomas Joseph about 1 month ago
- Follows deleted (Task #2917: System Test Results and Reports )
TJ Updated by Thomas Joseph about 1 month ago
- Follows deleted (Task #2945: Testing)
TJ Updated by Thomas Joseph about 1 month ago
- Due date changed from 29/01/2026 to 27/01/2026
- Start date changed from 27/01/2026 to 23/01/2026
DT Updated by Dhanasekar T about 1 month ago ยท Edited
- % Done changed from 0 to 100
Device Delivered to customer
TJ Updated by Thomas Joseph about 1 month ago
- Status changed from Analysis Started to Resolved
Actions